Blog

Pellet Loss Regulation (EU) 2025/2365: obligations, deadlines and who is affected

Any business that handles five tonnes of plastic pellets or more a year falls under Regulation (EU) 2025/2365. It is usually called the Pellet Loss Regulation or the EU plastic pellet regulation. The first obligation has applied since 16 December 2025, most of the others follow on 17 December 2027.

What the regulation is called

The official title is “Regulation (EU) 2025/2365 on preventing plastic pellet losses to reduce microplastic pollution”.1 In practice you will read Pellet Loss Regulation, plastic pellet regulation, EU pellet regulation or just the number 2025/2365. They all mean the same rule. In German it goes by Kunststoffgranulat-Verordnung.

As an EU regulation it applies directly in all 27 Member States. No national law is needed to transpose it. It was published in the Official Journal on 26 November 2025 and entered into force on 16 December 2025.

Who is affected

The regulation names four groups (Article 1(2)):

  • businesses that handled five tonnes of plastic pellets or more in the EU in the previous calendar year
  • operators of installations that clean pellet containers and tanks, regardless of quantity
  • carriers that transport pellets by road, rail or inland waterway, including carriers from outside the EU
  • in maritime transport, shippers and the operators, agents and masters of seagoing vessels; for them the regulation applies only from 17 December 2028

For most businesses the first group is the one that matters. Five tonnes is 200 bags of 25 kilograms, or five one-tonne big bags.

What counts as plastic pellets

The definition is broad: any mass of polymer-containing material produced for moulding in plastic product manufacturing, regardless of its shape, form or size (Article 2(1)). The recitals list granules, flakes, powders, beads and agglomerates, of primary or secondary origin (recital 3). So recycled pellets are covered, and regrind and flakes can be as well. Dust from processing that is not reused does not count (recital 4).

What “handling” means

More than processing. The regulation lists production and recycling, compounding, conversion, processing, distribution, storage, packaging and transport (recital 15). A distributor that stores and moves bagged pellets is covered from five tonnes, just like an extrusion plant.

In our survey of 396 plastics businesses in November 2026, some thought regrind was exempt or that distributors were only indirectly affected.5 The text supports neither view.

Which year counts

The previous calendar year always decides. When the main obligations start on 17 December 2027, the quantity handled in 2026 is what counts. The regulation does not say how exactly the five tonnes are to be counted. We read the wording (“in the Union”) to mean that all sites of a company are added together.

What has applied since 16 December 2025

One obligation already applies to everyone in scope: avoid losses. If pellets reach the environment anyway, the business must take immediate action to contain them and clean them up (Article 3(1)).

Whether two further obligations from Article 5(6) already apply depends on the language version:

  • training staff so that they know their role, the equipment and the procedures
  • keeping yearly records of the quantity of pellets handled and the estimated losses, and retaining them for five years

The language versions differ here. The English, French and several other versions bring forward only the second subparagraph of Article 5(6), the part on the standardised estimation method. Under them, training and yearly records become mandatory on 17 December 2027 (Article 26). The German version applies the whole of Article 5(6) from 16 December 2025. All language versions are equally authentic. To be on the safe side, start training and record-keeping now.

By 17 December 2026 the European Commission is to publish free training material (Article 17(1)).

What applies from 17 December 2027

From that day the regulation applies in full. For every business in scope with its own installation this means:

  1. Notify the installation. Each site is notified to the competent authority, stating whether the annual quantity there is below 1,500 tonnes or not (Article 3(2)).
  2. Draw up a risk management plan. One for each installation, in line with Annex I.
  3. Put equipment and procedures in place. What the plan describes must exist on site. The order of priority is fixed: first prevent spills, then contain them, then clean up (Article 5(5)).
  4. Submit the plan and the self-declaration. The plan goes to the authority together with a self-declaration of conformity, using the model form in Annex II (Article 5(1)).
  5. Report incidents. After an incident or accident in which lost pellets affect human health or the environment, the authority must be informed without delay and within 30 days at the latest: estimated quantity, cause and measures taken (Article 14).

What goes into the risk management plan

Annex I sets out the content:

  • a site plan and the annual quantity
  • the locations where pellets could spill or leave the site, each rated high or low risk
  • the handling operations during which this could happen
  • a yearly estimate of how much was spilled and how much of it reached the environment
  • activities at suppliers, contractors and off-site storage that the business can influence
  • the person who records, investigates and reports spills
  • packaging, equipment and procedures

Equipment must be proportionate to the nature and size of the installation. Under Annex I, the minimum includes catchment devices such as spill trays and drain covers at high-risk locations, a vacuum cleaner for indoor and outdoor use, brooms and dustpans, and bins for collected pellets. Businesses that package pellets need sturdy, sift-proof packaging.

The plan has to be kept up to date. Businesses handling less than 1,500 tonnes per installation, and all microenterprises, submit an updated plan and a renewed self-declaration every five years (Article 5(2)).

Who needs a certificate

A certificate from a certifier is required only for installations that handled 1,500 tonnes or more in the previous year (Article 6). The deadline depends on the size of the company.2

CompanyCertificate byAfter that
Largeall larger companies17 Dec 2027every three years
Medium-sizedfewer than 250 staff, up to €50 million turnover or €43 million balance sheet total17 Dec 2028every four years
Smallfewer than 50 staff, up to €10 million17 Dec 2030valid for five years, then renew it or resubmit the plan every five years
Microfewer than 10 staff, up to €2 millionnone, in our readingplan every five years

Article 6 does not mention microenterprises. We read this to mean that they do not need a certificate, but the article does not say so explicitly. Installations below 1,500 tonnes need no certificate, whatever the size of the company.

Medium-sized and large companies with an installation of 1,500 tonnes or more also carry out a yearly internal assessment of whether the installation complies with the plan (Article 5(8)).

What is made public

The authorities publish notifications, risk management plans, self-declarations and certificates online, free of charge (Article 11). The annual quantity stated in the plan is not disclosed, and confidential business information stays protected. Even so, the plan should be written from the start so that customers, neighbours and competitors can read it.

Inspections and penalties

Authorities carry out inspections, including without prior notice (Article 13). Each Member State sets its own penalties. The regulation gives the framework: financial penalties must at least remove the economic benefit gained from the infringement. For the most serious infringements by companies, the maximum penalty must be at least 3% of annual turnover in the EU (Article 20).

In Germany the implementing act is still in preparation. Which authority will be responsible and how high the fines will be has therefore not been decided (as of November 2026).

Not to be confused with

Regulation (EU) 2023/2055 on microplastics. It added a restriction on microplastics to the chemicals regulation REACH and became known for the ban on loose glitter.3 For manufacturers and industrial users of pellets it brings a separate yearly report to the European Chemicals Agency (ECHA), due by 31 May each year. That report does not replace anything in the Pellet Loss Regulation.

Packaging regulation PPWR, (EU) 2025/40. It governs packaging and packaging waste. It has nothing to do with how pellets are handled on site.

Operation Clean Sweep (OCS). A voluntary programme of the plastics industry with the same aim. Businesses that take part have much of the groundwork done. The obligations under the regulation still apply.

What you can do now

  1. Record your quantity for 2026. Note the stock on 1 January and everything that came in during the year, for each site. With these figures you can answer the five-tonne question whichever counting method prevails.
  2. List your sites. Every hall and every outdoor store where pellets are kept or moved, including rented ones.
  3. Train staff and write it down. The German association TecPart and its partners have offered the free online training KARE since September 2026.4 The Commission’s own material is due by 17 December 2026. Keep a note of who was trained and when.
  4. Note spills. Date, location, rough quantity and whether anything left the site. This later becomes the yearly estimate.
  5. Schedule the plan for 2027. Walk the site, mark the risk locations, check the equipment. Anything missing must be bought and installed before 17 December 2027.

About PelletPlan. PelletPlan is software in development that takes small plastics businesses through these steps: check the obligations, walk round the site with a phone, record spills, create the plan and the self-declaration. So far there is a prototype, tested with sample businesses. We are looking for pilot companies to try it in 2027.

Apply as a pilot company

Sources

  1. Regulation (EU) 2025/2365, English version on EUR-Lex. All articles, annexes and recitals cited here refer to it.
  2. Commission Recommendation 2003/361/EC, size classes for micro, small and medium-sized enterprises
  3. Regulation (EU) 2023/2055, restriction of synthetic polymer microparticles under REACH
  4. TecPart, press release on the KARE training (in German)
  5. Our own survey of 396 plastics businesses, November 2026. Small, self-selected sample.